Equipment ready for transport from manufacturer's yard. Photo: Melbana Energy Limited
Australia’s Melbana Energy Limited has released an update on the progress of drilling operations at its Alameda-1 well, Block 9 PSC. Work will begin on September 13, 2021, subject to the remaining equipment, materials, and staff arriving in Cuba on schedule.
The Company owns a 30% interest in the 236 million barrels (best estimate) being tested in this drilling program. The Block 9 program comprises two exploration wells testing four separate targets. Materials and equipment have been received in Cuba and transported to the location near Varadero. Other materials and equipment are expected to arrive this week.
The support staff of the drilling operations has been hired and their travel arrangements are in the process of being completed.
Melbana has completed the drilling rig inspection. Several issues identified in the inspection are being addressed and not expected to impact the start date of drilling.
Preparations and discussions for the second exploration well, Zapato-1, are underway.
Sherritt International, Melbana’s drilling contractor will provide its Rig No. 1 for use in the Block 9 drilling program.
From our staff writers and editors.
Cuba took center stage at the 17th BRICS 2025 in Rio de Janeiro this weekend,…
Cuba has confirmed the 41st edition of the Havana International Fair (FIHAV 2025) will take…
WestJet CEO Alexis von Hoensbroech met Wednesday with Cuban President Miguel Díaz-Canel in Havana, a high-level meeting…
Cuba is ramping up efforts to address energy shortages through the expansion of photovoltaic solar…
Renowned Cuban pianist Marcos Madrigal has been named Chevalier de l’Ordre des Arts et des Lettres by…
Russia will provide funding of $1 billion dollars for investment projects in Cuba, according to…